Mustafa Shahmalak
14205 Avatar Ln, Boyds, MD, 20841
Customer
Primary contact and account details
Site & Utility
Service address, AHJ, and utility
System & Sales
Equipment and sales context
Permit
AHJ permit application & approval
Interconnection
Utility interconnection application
Inspection
Final electrical / building inspection
Meter / PTO
Meter change and Permission to Operate
Quick edit
Update workflow status, ownership, next action, and blockers. Every change is audited.
Notes & next actions
Operational log entries against this project
- general9 hours ago · Admin
We are following up with PEPCO and awaiting their response for PTO currently they application is in technical reviews
- general6 days ago · Admin
[Meter workbook] We are following up with PEPCO and awaiting their response for PTO currently they application is in technical reviews
- general6 days ago · Admin
[Meter workbook] We are following up with PEPCO and awaiting their response for PTO currently they application is in technical reviews
- general6 days ago · Admin
11.10 - 1st Payment Received
- general6 days ago · Admin
Emailed SR for info
- general6 days ago · Admin
11.10 - 1st Payment Received
- general6 days ago · Admin
All req docs sent to HOA again 1/14, fu done 1/23, fu done 1/29
- general6 days ago · Admin
We are following up with PEPCO and awaiting their response for PTO currently they application is in technical reviews
Status timeline
Every recorded change to permit, interconnection, inspection, meter, and PTO
- permitMay 7, 2026 at 8:04 PMAPPROVED → APPLIEDvia import · Admin
- interconnectionMay 7, 2026 at 8:04 PMNOT_STARTED → APPROVEDvia import · Admin
- permitMay 7, 2026 at 8:04 PMSet to APPROVEDvia import · Admin
- ptoMay 7, 2026 at 8:03 PMSet to NOT_STARTEDvia import · Admin
- meterMay 7, 2026 at 8:03 PMSet to REQUESTEDvia import · Admin
- interconnectionMay 7, 2026 at 8:03 PMSet to NOT_STARTEDvia import · Admin
Source files
Spreadsheet rows that contributed to this record
- Updated 4 Meter change (1).xlsx· sheet Sheet1 · row 9· imported May 13, 2026 at 12:24 PM
- Merged_Portfolio_Standard_Template.csv· sheet Sheet1 · row 77· imported May 7, 2026 at 8:50 PM
- Merged_Portfolio_Standard_Template.csv· sheet Sheet1 · row 77· imported May 7, 2026 at 8:41 PM
- Project Tracker New.xlsx· sheet Sheet352 · row 32· imported May 7, 2026 at 8:04 PM
- Project Tracker New.xlsx· sheet DO NOT EDIT · row 651· imported May 7, 2026 at 8:04 PM
- Updated 2 Meter change.xlsx· sheet Sheet1 · row 9· imported May 7, 2026 at 8:03 PM