Lisa Terry
2935 Mills Avenue NE, Washington, DC, 20018
Customer
Primary contact and account details
Site & Utility
Service address, AHJ, and utility
System & Sales
Equipment and sales context
Permit
AHJ permit application & approval
Interconnection
Utility interconnection application
Inspection
Final electrical / building inspection
Meter / PTO
Meter change and Permission to Operate
Quick edit
Update workflow status, ownership, next action, and blockers. Every change is audited.
Notes & next actions
Operational log entries against this project
- general6 days ago · Admin
$0 PPA
- general6 days ago · Admin
As per SR Good afternoon. I responded to this previously. This is a small multi unit apartment building and is not part of an HOA.
- general6 days ago · Admin
$0 PPA
- general6 days ago · Admin
As per SR
- general6 days ago · Admin
$0 PPA
- general6 days ago · Admin
As per SR
- general6 days ago · Admin
Required Transformer upgradation to proceed with orignal system size 11.4 KW AC and the cost is $15,524.76. Downsize option available is 9.09 KW AC to proceed without upgrades. i informed Bob and he asked me to tell the team to make designs with 9.09 KW AC I informed design team.
Status timeline
Every recorded change to permit, interconnection, inspection, meter, and PTO
- permitMay 7, 2026 at 8:12 PMNOT_STARTED → APPLIEDvia import · Admin
- interconnectionMay 7, 2026 at 8:04 PMAPPLIED → NOT_STARTEDvia import · Admin
- permitMay 7, 2026 at 8:04 PMAPPLIED → NOT_STARTEDvia import · Admin
- interconnectionMay 7, 2026 at 8:03 PMSet to APPLIEDvia import · Admin
- permitMay 7, 2026 at 8:03 PMSet to APPLIEDvia import · Admin
Source files
Spreadsheet rows that contributed to this record
- Merged_Portfolio_Standard_Template.csv· sheet Sheet1 · row 60· imported May 7, 2026 at 8:50 PM
- Merged_Portfolio_Standard_Template.csv· sheet Sheet1 · row 60· imported May 7, 2026 at 8:41 PM
- Projects status - 3 (1).xlsx· sheet 2026 · row 8· imported May 7, 2026 at 8:12 PM
- Project Tracker New.xlsx· sheet 2026_PROJECTS_UPDATES · row 61· imported May 7, 2026 at 8:04 PM
- Project Tracker New.xlsx· sheet 2026_PROJECTS_UPDATES · row 51· imported May 7, 2026 at 8:04 PM
- Project Tracker New.xlsx· sheet 2026_PROJECTS_UPDATES · row 36· imported May 7, 2026 at 8:04 PM
- Updated 2 InterconnectionWorkbook1-1.xlsx· sheet Sheet1 · row 7· imported May 7, 2026 at 8:03 PM
- Projects status - 3.xlsx· sheet 2026 · row 8· imported May 7, 2026 at 8:03 PM