Brittley Odom
2809 Lewis Ave, Suitland, MD, 20746
Stage: OnboardingRisk: LowUpdated 6 days ago
Customer
Primary contact and account details
NameBrittley Odom
Emailbrittley.odom@gmail.com
Phone7864793705
Utility account—
Loan / FinanceCity Renewable 0 cent PPA
Site & Utility
Service address, AHJ, and utility
Street2809 Lewis Ave
City / State / ZIPSuitland, MD, 20746
County / AHJPrince George's County
UtilityThe Potomac Electric Power Company (PEPCO)
System & Sales
Equipment and sales context
System size7.48 kW
ModulesSEG-440-BTD-BG
InverterUSE11400H-USSKBEZ8 ( 5700W )
Sales officeCity Renewables
Sales repmichaelvulcain@cityrenewables.com
Owner—
Permit
AHJ permit application & approval
StatusAwaiting AHJ
Applied—
Approved—
NotesPlans have been uploaded for review.
Interconnection
Utility interconnection application
StatusApplied
AppliedApr 7, 2026
Approved—
NotesPEPCO has the interconnection application in their record from Informed Prany and Bob they are contacting the customer
Inspection
Final electrical / building inspection
StatusNot Started
Scheduled—
Passed—
Notes—
Meter / PTO
Meter change and Permission to Operate
Meter changeNot Started
Meter requested—
Meter completed—
PTONot Started
PTO issued—
Notes—
Quick edit
Update workflow status, ownership, next action, and blockers. Every change is audited.
Edits are saved with full audit trail.
Notes & next actions
Operational log entries against this project
- general6 days ago · Admin
$0 PPA
- general6 days ago · Admin
As per SR
- general6 days ago · Admin
PEPCO has the interconnection application in their record from Informed Prany and Bob they are contacting the customer
Status timeline
Every recorded change to permit, interconnection, inspection, meter, and PTO
- permitMay 7, 2026 at 8:12 PMNOT_STARTED → IN_REVIEWvia import · Admin
- permitMay 7, 2026 at 8:04 PMIN_REVIEW → NOT_STARTEDvia import · Admin
- interconnectionMay 7, 2026 at 8:03 PMSet to APPLIEDvia import · Admin
- permitMay 7, 2026 at 8:03 PMSet to IN_REVIEWvia import · Admin
Source files
Spreadsheet rows that contributed to this record
- Merged_Portfolio_Standard_Template.csv· sheet Sheet1 · row 13· imported May 7, 2026 at 8:50 PM
- Merged_Portfolio_Standard_Template.csv· sheet Sheet1 · row 13· imported May 7, 2026 at 8:41 PM
- Projects status - 3 (1).xlsx· sheet 2026 · row 41· imported May 7, 2026 at 8:12 PM
- Project Tracker New.xlsx· sheet 2026_PROJECTS_UPDATES · row 111· imported May 7, 2026 at 8:04 PM
- Updated 2 InterconnectionWorkbook1-1.xlsx· sheet Sheet1 · row 17· imported May 7, 2026 at 8:03 PM
- Projects status - 3.xlsx· sheet 2026 · row 41· imported May 7, 2026 at 8:03 PM