Project Operations
Customer Operations Tracker
Back to projects
Commerice Kee
7508 Jaffrey Rd, Fort Washington, MD, 20744
Stage: OnboardingRisk: LowUpdated 6 days ago
Customer
Primary contact and account details
NameCommerice Kee
Emailcommericekee@gmail.com
Phone3017939327
Utility account—
Loan / FinanceLightreach
Site & Utility
Service address, AHJ, and utility
Street7508 Jaffrey Rd
City / State / ZIPFort Washington, MD, 20744
County / AHJPrince George's County
UtilityThe Potomac Electric Power Company (PEPCO)
System & Sales
Equipment and sales context
System size12.32 kW
ModulesSilfab 440W QD
InverterEnphase IQ8AC
Sales officeGreenBrilliance
Sales repdawit@greenbrilliance.com
Owner—
Permit
AHJ permit application & approval
StatusApproved
Applied—
Approved—
Notesboth permit issued - sent for installation 4/30
Interconnection
Utility interconnection application
StatusApproved
Applied—
Approved—
Notes—
Inspection
Final electrical / building inspection
StatusNot Started
Scheduled—
Passed—
Notes—
Meter / PTO
Meter change and Permission to Operate
Meter changeNot Started
Meter requested—
Meter completed—
PTONot Started
PTO issued—
Notes—
Quick edit
Update workflow status, ownership, next action, and blockers. Every change is audited.
Edits are saved with full audit trail.
Notes & next actions
Operational log entries against this project
- general6 days ago · Admin
3.13.26
- general6 days ago · Admin
As per SR
Status timeline
Every recorded change to permit, interconnection, inspection, meter, and PTO
- interconnectionMay 7, 2026 at 8:04 PMSet to APPROVEDvia import · Admin
- permitMay 7, 2026 at 8:03 PMSet to APPROVEDvia import · Admin
Source files
Spreadsheet rows that contributed to this record
- Merged_Portfolio_Standard_Template.csv· sheet Sheet1 · row 23· imported May 7, 2026 at 8:50 PM
- Merged_Portfolio_Standard_Template.csv· sheet Sheet1 · row 23· imported May 7, 2026 at 8:41 PM
- Projects status - 3 (1).xlsx· sheet 2026 · row 27· imported May 7, 2026 at 8:12 PM
- Project Tracker New.xlsx· sheet 2026_PROJECTS_UPDATES · row 86· imported May 7, 2026 at 8:04 PM
- Projects status - 3.xlsx· sheet 2026 · row 27· imported May 7, 2026 at 8:03 PM