Project Operations
Back to projects

Deborah Thompson

9114 Rolling View Dr, Lanham, MD, 20706

Stage: OnboardingRisk: LowUpdated 9 hours ago

Customer

Primary contact and account details

NameDeborah Thompson
Emaildeboraht818@yahoo.com
Phone2404325263
Utility account
Loan / FinanceIGS Solar

Site & Utility

Service address, AHJ, and utility

Street9114 Rolling View Dr
City / State / ZIPLanham, MD, 20706
County / AHJPrince George's County
UtilityBaltimore Gas & Electric Co

System & Sales

Equipment and sales context

System size5.28 kW
ModulesSilfab 440W QD
InverterUSE5700H-USMNBE78
Sales officeNusun Power
Sales repYfulladi@nusunpower.com
Owner

Permit

AHJ permit application & approval

StatusApproved
Applied
Approved
NotesApproved docs in DB.

Interconnection

Utility interconnection application

StatusApproved
Applied
Approved
Notes

Inspection

Final electrical / building inspection

StatusNot Started
Scheduled
Passed
Notes

Meter / PTO

Meter change and Permission to Operate

Meter changeNot Started
Meter requested
Meter completed

PTONot Started
PTO issued
Notes

Quick edit

Update workflow status, ownership, next action, and blockers. Every change is audited.

Edits are saved with full audit trail.

Notes & next actions

Operational log entries against this project

  • general9 hours ago · Admin

    This is IGS project. For this project US teams provides the list for the approved customer then we will apply the meter change. This customer is not listed in the approved provided meter change list by IGS. This is why meter change is on hold

  • general6 days ago · Admin

    [Meter workbook] This is IGS project. For this project US teams provides the list for the approved customer then we will apply the meter change. This customer is not listed in the approved provided meter change list by IGS. This is why meter change is on hold

  • general6 days ago · Admin

    [Meter workbook] This is IGS project. For this project US teams provides the list for the approved customer then we will apply the meter change. This customer is not listed in the approved provided meter change list by IGS. This is why meter change is on hold

  • general6 days ago · Admin

    11.6 - Approved -PJ

  • general6 days ago · Admin

    as per SR

  • general6 days ago · Admin

    11.6 - Approved -PJ

  • general6 days ago · Admin

    as per SR

  • general6 days ago · Admin

    This is IGS project. For this project US teams provides the list for the approved customer then we will apply the meter change. This customer is not listed in the approved provided meter change list by IGS. This is why meter change is on hold

Status timeline

Every recorded change to permit, interconnection, inspection, meter, and PTO

  • permitMay 7, 2026 at 8:04 PM
    IN_REVIEWAPPROVED
    via import · Admin
  • interconnectionMay 7, 2026 at 8:04 PM
    Set to APPROVED
    via import · Admin
  • permitMay 7, 2026 at 8:04 PM
    Set to IN_REVIEW
    via import · Admin
  • meterMay 7, 2026 at 8:03 PM
    Set to NOT_STARTED
    via import · Admin
  • ptoMay 7, 2026 at 8:03 PM
    Set to NOT_STARTED
    via import · Admin

Source files