Project Operations
Back to projects

Cynthia Gray

7603 Georgian Dr, Upper Marlboro, MD, 20772

Stage: OnboardingRisk: LowUpdated 6 days ago

Customer

Primary contact and account details

NameCynthia Gray
Emailcdgsystemic@gmail.com
Phone2408826336
Utility account
Loan / FinanceIGS Solar

Site & Utility

Service address, AHJ, and utility

Street7603 Georgian Dr
City / State / ZIPUpper Marlboro, MD, 20772
County / AHJPrince George's County
UtilityThe Potomac Electric Power Company (PEPCO)

System & Sales

Equipment and sales context

System size10.08 kW
ModulesSEG-420-BTD-BG
InverterEnphase IQ8AC
Sales officeJonathan Ngo
Sales repaaron@greenbrilliance.com
Owner

Permit

AHJ permit application & approval

StatusNot Started
Applied
Approved
NotesB-permit ready for payment - once paid it will be issued in few days 5/5

Interconnection

Utility interconnection application

StatusApplied
AppliedApr 28, 2026
Approved
NotesNA

Inspection

Final electrical / building inspection

StatusNot Started
Scheduled
Passed
Notes

Meter / PTO

Meter change and Permission to Operate

Meter changeNot Started
Meter requested
Meter completed

PTONot Started
PTO issued
Notes

Quick edit

Update workflow status, ownership, next action, and blockers. Every change is audited.

Edits are saved with full audit trail.

Notes & next actions

Operational log entries against this project

  • general6 days ago · Admin

    4.30 - Changed from IGS to GL | APPROVED 5.2.25

  • general6 days ago · Admin

    form sent for sign to HO

  • general6 days ago · Admin

    form sent for sign to HO

  • general6 days ago · Admin

    4.30 - Changed from IGS to GL | APPROVED 5.2.25

  • general6 days ago · Admin

    4.30 - Changed from IGS to GL | APPROVED 5.2.25

  • general6 days ago · Admin

    form sent for sign to HO

  • general6 days ago · Admin

    APPROVED 4.22.26

  • general6 days ago · Admin

    as per SR

  • general6 days ago · Admin

    NA

  • general6 days ago · Admin

    NA

Status timeline

Every recorded change to permit, interconnection, inspection, meter, and PTO

  • interconnectionMay 7, 2026 at 8:41 PM
    APPROVEDAPPLIED
    via import · Admin
  • interconnectionMay 7, 2026 at 8:04 PM
    APPLIEDAPPROVED
    via import · Admin
  • interconnectionMay 7, 2026 at 8:03 PM
    Set to APPLIED
    via import · Admin
  • permitMay 7, 2026 at 8:03 PM
    Set to NOT_STARTED
    via import · Admin

Source files